Location:
Mangalore, Karnataka
Year:
2013-2014
Major Structures:
- Heavy equipment foundations
- Utility trenches
- Pipe Racks
Area:
~ 25,000 square meter
Concrete:
~ 23,000 cubic meter
Structural Steel:
~ 2,500 metric tonne
Reinforcement Steel:
~ 2,500 metric tonne
Project Key Highlight:
Structural fabrication and erection of 5 TIRE heavy pipe rack of 1900 MT 30 days before the timeline.