Work Scope: 
                                        Civil & Structural
                                    Location: 
                                        Khopoli, Maharashtra
                                    Year: 
                                        2013-2014
                                    Major Structures:
                                        - Edible Oil Unit
 - Ancillary Structures
 - Pipe Racks
 - Roads
 
Area: 
                                        ~ 40,000 square meter
                                    Concrete: 
                                        ~ 18,500 cubic meter
                                    Structural Steel: 
                                        ~ 2,600 metric tonne
                                    Reinforcement Steel:
                                        ~ 2,000 metric tonne
                                    Project USP: 
                                        Structural work at height of 34 meter
                                    
                            
            